Phase 2 of Sewer District's Westside Extension Project Completed

Another milestone has been reached in expanding public sewer service around Chautauqua Lake. On Thursday, South and Center Chautauqua Lake Sewer District leaders celebrated the formal completion of Phase 2 of the district's Westside Sewer Extension, which began in 2024. District Director Thomas Walsh says the completion of this phase represents years of planning, engineering, and construction work...

Thomas Walsh: proud of the work done

The project began in 2017, when Vince Horrigan was Chautauqua County Executive. District board member Pierre Chagnon credited him for having the vision and commitment to see the project through...

Pierre Chagnon: pleased to reach the milesone

Phase 2 extends service along approximately 3.6 miles of Route 394 in the towns of North Harmony and Chautauqua, providing service to approximately 520 parcels. The third and final phase of the project will extend public sewer infrastructure from Point Chautauqua to Midway State Park.

 

Photo by Chautauqua County Government

comments powered by Disqus
Local Weather
Dunkirk, NY
--°
Keyword Search

Classic Hits 101.5FM - 1410AM & KIX Country 96.5FM - 100.3FM
4561 Willow Road | Dunkirk, New York 14048
Telephone: (716) 366-1410
Fax: (716) 366-1416
EEO Report  |  Public Inspection Files
WDOE, Dunkirk, NY & WBKX, Fredonia, NY
Copyright © 2026 Chautauqua Today
Classic Hits 1410 WDOE, Dunkirk, NY.
Site Designed by RiverBender.com
-->